This page, in the past, has suggested that it may be cheaper to build an elevated Red-Blue connector, and also cast doubt (twice!) on the MassDOT's cost estimates. Their claim is that it would cost $750 million to make the extension; which is a cost per mile of $3 billion. This per-mile cost is double the cost of recent tunnel projects in Seattle and San Francisco (where, as you may be aware, they have earthquakes) and even more than the Second Avenue Subway in New York. It's a completely outlandish number.
And this is entirely by design.
The state is required to plan the Red-Blue connector, but they're not actually required to build it. Because MassDOT is, at some levels, a morass of incompetence (see Extension, Green Line), they operate under the assumption that nothing new should ever be built, even if there are dramatic improvements to the overall transportation network. Remember, these are the same people who look at ridership growth and declare it "basically flat." But not only do they want to do as little as possible, they actively stack the deck against their designs to come in so costly that they don't make sense to build. This is the idea: inflate the cost so much that it would not make any sense to build. It's deceitful. It's duplicitous. And at MassDOT, it's standard operating procedure.
(On the other hand, when MassDOT—or MassHighway—wants to build something, like the outlandish mutil-tunneling of rail lines in Dorchester to add highway capacity to the Southeast Expressway, they don't bother to put forth a cost estimate. Or remember when we didn't add a lane to 128 because it was going to cost too much? Yeah, me neither.)
Here's how it's done. As we discussed, there is an existing tunnel to Joy Street which was used until the 1950s to move East Boston cars to the old Bennett Street Yards in Harvard Square for heavy maintenance. The obvious solution is to use as much of this tunnel as possible—both to minimize digging in the street and to minimize disruption to current service—yet the state's two alternatives don't use it at all. Instead, with minimal justification, they propose a half-mile-long deep bore tunnel 50 feet below grade, tying in with the existing tunnel just west of Government Center. Using tunnel boring machines (TBM) makes sense for tunnels of any length, as the impact to the surface is significantly less. It is also, for longer tunnels, significantly cheaper than cut-and-cover methods. It's fine to have that as one alternative—there are certainly advantages to using a TBM—but the fact that the alternative analysis only mentions TBMs makes it, well, not really an alternatives analysis at all.
The benefits of a TBM, however, only accrue for longer tunnels. The marginal cost of an extra foot of TBM tunnel is relatively low, but the initial cost is very high. A cut-and-cover tunnel here would require 1300 feet surface impact. Using a TBM would require less, but only slightly. Why? Because you still have to dig launch and recovery boxes for the TBM, and where the tunnel needs to be wider for stations or crossovers, it has to be dug out. Considering the substrate in Boston (mud and clay) a TBM would have to build concrete rings as it digs, and any stations or crossovers between the tunnels would have to be dug out separately. And while the total disruption would be somewhat less than a cut-and-cover tunnel, the disruption would be more spread out and extend much further, from Charles Circle to or beyond Government Center, rather than from Charles to Joy Street. Utilities would be affected in either scheme, and it's possible that fewer utilities would be affected by a more-contained scheme between Charles Circle and Joy Street.
So in addition to carving up nearly as much street space, and over a longer distance, you'd also incur the cost of using a tunnel boring machine (they're not cheap). You'd be building nearly a mile of new tunnel, while only incurring the benefit of about a quarter of that. And the costs are therefore much higher. This only makes sense if you don't actually want to ever build anything. [Update 11/2017: I've heard through the grapevine that part of the reason only TBMs were analyzed is that Mayor Menino didn't want anyone digging up the new streetscape on Charles Street, which he liked. The trees are nice for people driving cars, I guess. 10 years later, the road is a potholed mess, so dig, baby, dig.]
MassDOT's plan would also build tail tracks under Charles Circle beyond the station. Tail tracks are important: it allows a terminal to continue to operate at full capacity even if a train is incapacitated: it can be shoved in to the tail track and out of the way until the end of service (or until service levels are decreased). However, they take up a good deal of space. This is less of an issue if there is extra space (like there is at Forest Hills, Wonderland or Oak Grove) or at Alewife, where the line was originally built to extend to Arlington (the tail tracks actually do cross the border). But in downtown Boston, the tail tracks require significant extra tunneling under Charles Circle, which is expensive and disruptive.
A different, more outside-the-box option is to create a "pocket track" before the final station. This serves the same purpose as the tail track—train storage near the end of the line—but rather than two long tails, it is in the middle of the two tracks short of the station. All this requires is that the tunnel be built wider here (the same width as the platform to the west requires) for this staging track. Additionally, by utilizing the existing layout at Bowdoin (with, perhaps, some modification for longer trains inbound, or even converting the station to outbound service only), the line would retain the utility of the loop there, which is eliminated in both of the state's alternatives. While this does result in slower operation in and out of the station, it allows redundancy for turning trains: if there is any congestion or another issue at Bowdoin, some or all trains can be turned temporarily at Government Center to maintain service on the rest of the line. Eliminating this loop eliminates any such redundancy. A pocket track and the retention of the loop are nearly impossible with a bored tunnel but with cut-and-cover simply requires a somewhat wider dig.
By requiring long-term construction closure of the line west of Government Center, the state's plan would also require new construction of a terminal station there. Government Center does have a crossover to its east, but it is a single crossover, which would not be able to handle the rush hour Blue Line schedule. This would require a new double crossover to be installed in what is a narrow section of tunnel. Utilizing the existing tunnel past Bowdoin would preclude this extra cost, as trains could continue to loop there during construction. There would be no disruption when the extension opened—not even a weekend shutdown to tie in new tracks. The same can't be said for the State's scheme.
State's plan in red, my plan in blue. |
- A launch box for the TBM
- Cut-and-cover tail tracks west of Charles Station
- Main access to the Charles Station (planned 50' below grade)
- Charles Station, proposed as a sequentially excavated cavern but with no explanation of how that will be done in the fill-and-clay substrate in the area.
- Emergency egress from Charles Station
- Crossovers east of Charles Station
- New Bowdoin Station (alternative 2 only)
- Modification of existing Bowdoin Station and trackage to serve as ventillation (alternative 1 only)
- Receiving shaft for Bowdoin station
- Cut-and-cover track for connection to existing track at Government Center
- New crossover west of Government Center to allow it to serve as a terminal station
- Total cut-and-cover of approximately 800 feet, assuming the Charles Station can be built below grade (I'm skeptical).
And here's a rundown of the elements required for a cut-and-cover tunnel from Joy Street to Charles Circle:
- Main access to Charles Station (20' below grade)
- Charles Station cut-and-cover
- Secondary access to Charles Station (possible because it would require only 20' of vertical circulation, rather than 50')
- Cut-and-cover crossovers and pocket track
- Cut-and-cover connection to existing tail tracks at Joy Street
1. Utility Relocation: 0.25 miles at $100m/mi = $25m
2. Cut-and-cover tunnel (mostly 40' wide): 0.25 mi at $600m/mi = $150m
3. Rail systems: 0.25 mi at $100m/mi = $25m
4. Egress, NFPA130, etc: 0.25 mi at $200m/mi = $50m
5. Station, 1 at $50m = $50m
6. Street rebuilding, 0.33 mi at $75m/mi = $25m
This totals to $375 million, or half of what the state's plan would cost. There's no way to know much the state thinks it would cost, because they didn't bother to analyze this alternative as part of their alternatives analysis.
Now, the state did address the difference in cost between a bored tunnel and a cut-and-cover tunnel. Well, sort of. The draft environmental impact report has the clause:
The resulting total cost (direct plus offsets) to construct a cut-and -cover tunnel shell is about 1.2 times the cost of the mined tunnel method. This differential may slightly decrease when the balance of construction scope (e.g., station components common to both Build Alternatives) is considered. Based on this relative cost differential and the associated environmental and social impacts, schemes utilizing mining methods were selected for further development and evaluation.Uh, this isn't really how an alternatives analysis works. In a complex construction project, 20% is basically a margin of error. As we've seen in some other deep boring construction, it's not uncommon to have an unforeseen obstruction which can dramatically increase the cost of a project. This can also be an issue with a cut-and-cover tunnel, although Cambridge Street was widened in the 1920s so the utilities there are a bit less complex than the centuries-old sewers under many Boston streets. The point of an alternatives analysis is too look at different alternatives and see which is the most appropriate. In this case, there are not enough alternatives, and very little actual analysis. I wouldn't be surprised if a full analysis showed that 1300 feet of a cut-and-cover tunnel was a good deal less expensive than twice as much deep bore tunnel and the additional track connections involved.
And there is no information in this report about how they are going to build the Charles Blue Line Station 50 feet underground in the substrate of Boston with sequential mining. The Second Avenue Subway is being built in hard Manhattan schist which can be blasted apart while still maintaining structural integrity above. I'm not an engineer with this sort of experience, but given that there is no explanation of how it would take place, I'd have to doubt its veracity. The current idea is explained that the tunnels would be bored and then the station areas would be mined out in between the bored tunnels, using their structure to support the road above. I guess that could work. But it seems to add several steps (and thus increase the cost) by building the tunnels only to hack them apart to build space for stations and crossovers in between. When asked in 2011 if it was inflating the costs of the project, MassDOT was very defensive in claiming that they weren't, and that Very Important People said the same thing, yet they didn't actually explain why they chose the scheme that they did (beyond "we hired someone") and as I outline here, it seems they put their thumb on the scale.
Even giving them the benefit of the doubt that a bored tunnel is the best option, the cost estimates seem out of hand. The cost of the 72nd Street Station cavern—which is 1300 feet long, the length of the Red-Blue connector from Charles to Joy Street—plus the track connections to 63rd Street is $431 million, significantly less than the Red-Blue connector. This, for a project taking place 100 feet below the street in New York City, which may be the most expensive construction market in the world.
To put it another way, I find it very hard to fathom that a ¼ mile cut-and-cover tunnel with a single station (for which the headhouse is already built) connecting in to an existing tunnel would cost three quarters of a billion dollars. Or $3 billion per mile. Some more comparisons? The cost of the Longfellow Bridge—twice as long, and rebuilding a century-old bridge while maintaining transit service—is one third the projected cost of Red-Blue. That can't be right. The Big Dig cost less than $3 billion per mile, to build highway tunnels three times as wide, over and under several active railroad tunnels, with more ventilation and dozens of ramps. And the Red-Blue connector would cost as much? Please.
A layman's staging plan for Red-Blue. Simplified, a bit. |
See larger-size file here |
There is no logical reason that the Red-Blue connector should be, per mile, the most expensive subway construction in the country. Unless it's by design. And—yes, to point a finger at MassDOT—that's exactly what I think has happened.
tl;dr: this is why we can't have nice things.
Yet more reprehensible abuse of the public trust by MassDoT and the administration (not that MassDoT's behavior is unique to the present one). It's especially frustrating since it means that we won't be able to trust the NSRL feasability study in light of Baker and Pollack's opposition and that MassDoT is willing to compromise the region's future for God knows what.
ReplyDeleteAccording to Massbenchmarks, right now is the best time to do projects like this (https://urbanliberty.wordpress.com/2016/02/18/massbenchmarks-state-needs-transit-investment/) and, judging by the way the region's roads seem to be at or over capacity, any increase in the MBTA's capacity or connectivity is going to have huge gains for the T.
I don't want to go easy on the mbta or massdot (see extension, green line) but there really is no upside for the mbta to expand service since the only metric "people" judge the mbta on is whether the lose money or not, and that judgement is based on sales tax revenues(!). The blame need to go back to the legislature and the governor, who need to tell the mbta that these things are needed and fund them.
ReplyDeleteAlso, I thought tail tracks are also useful so that the train doesn't have to slow so much before entering the last station, and therefore helping potential headways.
Every other train coming in to a station with a crossover before it has to slow for the crossover (SOP for the T, except at Ashmont and Wonderland), so there are no savings there. This could probably be solved with signal logic, with an approach signal leading to the platform and a restricted signal once there. Tail tracks may save a few seconds, but at what cost? If need be the northernmost track could be built a bit longer to allow more favorable signals, but there's a pretty quick cost-benefit tradeoff here.
DeleteIf the only metric transit is judged on is how much money it makes, then maybe someone nearby (cough MGH cough) might have interest in better access to its facility.
Comments re: train storage. . .
ReplyDeleteBowdoin Station and the loop have to be partially demolished to continue the tunnel on-alignment. It's one of the tightest loops on the system, and would be a huge speed clog and headway limiter if all trains in and out of Charles MGH station had to ride a half-loop's curve. As speed-restricted as Harvard curve on the Red Line if the trains are just passing through; twice as speed-restricted if an out-of-service set is being maneuvered for storage mid-loop. If Blue has a future being extended north to Lynn or beyond the loop is going to limit headways by making Blue more susceptible at peak load to bunching downtown near the end of an inbound run to Charles. That in turn is going to make on-platform turnbacks much harder to keep in balance for starting the outbounds on accurate headways than it is at Alewife, Forest Hills, Oak Grove, and Wonderland where everything that comes in can usually go immediately back out without schedule correction. You would need to stock more idling trainsets at Charles during peak load as schedule-correcting relief valve for keeping end-of-run inbound bunching from spilling over to start-of-run outbound bunching. The most precise signaling tech in the world is only going to paper that vulnerability to a certain extent; it'll be a perpetually brittle and exploitable concern. So the act of trying to preserve storage space by saving the loop ends up requiring you to build more total storage space. Not worth it when plowing through the west-end wall of the Bowdoin platform to keep to a straight tunnel alignment allows a fully at-speed tunnel and turnback platform that can behave at even keel for both directions a la Alewife or Forest Hills.
Pocket tracks are not going to be doable because you simply don't have enough length to do them right. Current end-of-track at S. Russell St. and the would-be end of the Charles MGH platform at the first piling for the Red Line El upstairs is 1075 ft. To fit 2 six-car trainsets of storage (WITHOUT any retained loop, per above) next to a 300 ft. platform you would have to cram in the tightest-possible turnouts, akin to Blandford St. yard on the B Line. That kind of compression is woefully inadequate for cycling trains out of service. Movements would be slow enough to induce a delay in another approaching train's headway. It would be practical enough for stuffing an out-of-service train that won't be moving again for awhile, but would not work for shift changes or staging run-as-directeds. Unlike Oak Grove and Wonderland where out-of-service trains just deadhead short-distance through the outskirts of the line to/from Wellington or Orient Heights yards, Charles on the other side of downtown will need to be set up as fluidly as Forest Hills and Alewife for hot-swapping in regular service from adjacent storage. And that means higher-speed, wider-spaced crossovers like Alewife Yard has (see pics here): https://sery2831.smugmug.com/Transit/Red-Line-Shots/i-ZD85z73/L. Alewife can summon an off-shift train to or from the platform at full speed without fouling the slot for an on-platform turnback with an excruciatingly slow crawl. It's also pre-provisioned to work as a fluid mid-line yard for slipping deadheads to/from Arlington if the line is extended. The crossover space needed at Charles to perform roughly similar end-of-line tasks at no ops penalty simply isn't available between S. Russell St. and the would-be Charles Under platform. Therefore, tail tracks are the only non-crippled way to build it if you want a Blue Line set up flexibly enough to extend north to Lynn at no future ill effects to downtown bunching.
Ironically, the only thing the stupid deep bore build has going for it is that by bypassing some old tunnel structures you probably would have the clean room to build a fluidly functional center pocket. But in no way would that price out better than cut-and-cover + tail tracks.
Alewife Yard has 10 mph crossovers as you can see pointed out in the same photo album. I'm also not sold on the value of tail tracks, after all, the Chuo Line terminal in Tokyo doesn't have them and still has no trouble turning over 20 tph, which is more than any rapid transit line in Boston.
DeleteChuo line does have tail tracks at Tokyo. They're not long enough to let a full train proceed beyond the end of the platform and park there, but they are long enough to allow trains to enter the platform at a higher speed than if they didn't exist and there were buffers at the end of the tracks.
DeleteThere's a pretty easy solution for Bowdoin: make it an outbound-only station. You could probably have one-way faregates turnstiles in that case. The outbound platform is six cars long, but the inbound barely 4 (I guess I hadn't realized how short it is!). Then Charles is a two-way station. That's probably cheaper than major infrastructure changes, although plowing through Bowdoin to straighten out the tracks might make more sense.
DeleteSigh... you could plow through, straighten out, and rebuild Bowdoin *after* building the extension.
DeleteWhat if the best bang for your buck isn't more infrastructure, but better bus service or even BRT around the city?
ReplyDeleteIt might be the most socially equitable/fair expenditure as well
Ask anyone who doesn't have a car how good MBTA bus service is. People who park and ride or come in through commuter rail stations just at peak commuting weekday times have no idea how good they have it.
I've always thought that the Urban Ring should not have died (as it apparently seems to have)
[See https://www.massdot.state.ma.us/theurbanring/images/LPA_Figure.pdf]
Lastly, there is no circular line on the MBTA and this BRT would function as such. It would also help the rest of the system function a bit better.
This blog has covered how BRT doesn't really work in Boston ad nauseam. BRT is certainly worth some investment, but due to the layout of the streets and their general narrowness, BRT is unlikely to ever supplant rail as the main workhorse in Boston (BRT can't scale well unless it has wide rights-of-way, which we don't have). The urban ring is a round-peg-square-hole situation (kind of like the Silver Line) using BRT to do something it's not particularly good for. Once you're on a separated ROW, especially in a tunnel, electrified rail service is far superior to buses for a number of reasons (tighter clearances, faster service, much less ventilation, etc).
DeleteBRT wouldn't function well as a circle because there's no coherent circle. The routes shown are generally no faster than going in and out of the core. Certain portions could have upgraded service, but to create service fast enough to compete with the rail system, you're talking about new rights-of-way, bridges and tunnels. Those get expensive real fast. Fast enough that you're better off doing things like the Red-Blue connector.
Great Blog Thank you so much for sharing this.
ReplyDeleteHikvision Full HD & Night Vision Camera Kit
Greetings I am so glad I found your blog page, I really found you by error, while I was researching on Aol for something else, Anyways I am here now and would just like to say many thanks for a marvelous post and a all round enjoyable blog (I also love the theme/design), I don’t have time to read it all at the moment but I have saved it and also added in your RSS feeds, so when I have time I will be back to read much more, Please do keep up the superb job.
ReplyDeletesafety decking systems
Hello just wanted to give you a quick heads up. The words in your article seem to be running off the screen in Safari. I'm not sure if this is a formatting issue or something to do with web browser compatibility but I figured I'd post to let you know. The design look great though! Hope you get the issue fixed soon. Kudos
ReplyDeleteIf you are going for finest contents like me, just go to see this site daily since it presents quality contents, thanks
ReplyDelete